Both questions refer to Domain B (Project Management).
1. The chain of activities in a plan that must begin and end on time in order to achieve project milestones and execute the project on schedule is a/an:
a. absolute agenda
b. critical path
c. schedule timeline
d. crucial series
2. The process that must be followed to utilize a project management procurement plan are: plan, ___________, administer, and close
a. conduct
b. research
c. negotiate
d. evaluate