Call for EMPI Entries/Nominations!
November 30, 2024
Submission Deadline — November 30th
Enter/Nominate

Membership 101
December 5, 2024
Complete Weddings + Events Headquarters
REGISTER

Overall Excellence Chapter Award

 

 

MPI MN November 2021 CMP Prep Questions

By: Denise Woods, CMP | Nov 12, 2021

Both questions refer to Domain B (Project Management).

1.  The chain of activities in a plan that must begin and end on time in order to achieve project milestones and execute the project on schedule is a/an:
a.  absolute agenda
b.  critical path
c.  schedule timeline
d.  crucial series

2.  The process that must be followed to utilize a project management procurement plan are:  plan, ___________, administer, and close
a.  conduct
b.  research
c.  negotiate
d.  evaluate

Answers: 
1.  b
2.  a
 
 

Author

Denise Woods
Denise Woods, CMP


 

 

 

 

 

Connect with Us

Chapter Advertisement

Job Postings


MORE JOBS

 

 

 

Chapter Advertisement